Ocean Outfalls
Ocean Outfall Design & Engineering
Location: Ventura, California









L123 was contracted to design and to provide engineering support for an Ocean Outfall construction project in Ventura, California. The outfall and associated pipeline will serve to dispose of treated effluent from the expanded wastewater treatment facility. The project consists of two components: the onshore Conveyance Pipeline and the offshore Ocean Outfall Pipeline. The underground Conveyance Pipeline traverses approximately 2 miles under neighborhood streets then under the harbor via horizontal directional drilling (HDD) to a city park, where it then connects to the ocean outfall pipeline. The 20-inch outside diameter HDPE Ocean Outfall Pipeline runs from a vault in the park to the terminus 6,950 feet offshore in 54 feet of water. The HDD segment runs through an HDD boring underneath the beach and approximately 80 to 100 feet under the seafloor to its exit point on the seafloor approximately 4,500 feet offshore of the park in 48 feet of water. The offshore end of the HDD-installed outfall pipeline is connected to a seafloor pipeline segment 2,083 feet in length and terminates in 53 feet of water. The offshore termination of the seafloor segment connects to a 272-foot-long diffuser segment of HDPE pipe with diffuser ports.
Water Treatment Plant Intake and Outfall Facility Decommissioning
Location: Ventura, California


















Municipal Wastewater Outfall Construction Project
Location: Cayucos, California






















San Elijo Joint Powers Authority Outfall Stabilization Project
Location: Carlsbad, California








This project involved the stabilization of a reinforced concrete outfall pipeline offshore Carlsbad, California. Approximately 2,000 feet of this 48-inch diameter pipeline was precariously suspended above the seafloor and required stabilization. The project site spanned an active surf zone. Environmental restrictions precluded the use of beach or shore-based support systems such as a trestle or pier, and the surf zone was too active to permit the use of floating equipment. L123’s owner, Mark Steffy, conceived and developed the Surf Sled II support system. Steffy also conceived and directed the design of a unique pipe support system. After soliciting 71 engineering firms nationwide, and reviewing a short list of eight responses, the Surf Sled approach was judged by the owner to be the most practical, safe and economical solution. According to the client, the project concept and execution saved the client over $20 million dollars. The surf sled used on this project was the second of three surf sleds designed, constructed and operated by Mark Steffy. The project was the subject of multiple technical papers, articles in trade journals, and presentations.
This project demonstrates the ability of L123 to plan and execute major pipeline work in a nearshore or surf zone condition. It also demonstrates the ability of L123 to conceptualize and execute solutions to challenging underwater project requirements.
Pemex Dos Bocas 24-inch Diameter Outfall Construction Project
Location: Paraiso, Tabasco, Mexico








Project Description
This project was highly challenging due to the length (2.2-kms) and weight (approx 1,500-tons) of the pipeline, the dynamic coastal environment in which it was installed (coastal surf zone), the offshore water depths involved (excess of 20-m), the substantial project administrative support required by Pemex procedures, and the location of the work to very sensitive nearby existing Pemex pipeline infrastructure (three 36-inch export pipelines and five 48-inch diameter field pipelines). The HDPE outfall pipeline was pre-assembled in ten sections onshore and then pulled offshore in two extended operations (beach-pull). The actual marine installation required extensive around-the-clock operations involving over 250 skilled workers split into two offshore crews and two onshore crews. Final assembly involved fusing together the ten sections, installation of concrete ballast weights, and installation of flotation. The pipeline installation methodology was based on floating the pipeline into position and then flooding and sinking the pipeline. The pipeline was launched from the shoreline using a rail system. Pemex is the Mexican national oil company. ARB-Arendal is a Mexican pipeline company with an American corporate partner. ARB-Arendal performs in excess of $100,000,000 USD of pipeline construction annually in Mexico.
Outfall Repair Project
Location: Oxnard, California






